Foundry Lane Fitout — completed open-plan office with glazed meeting rooms

Commercial Fitout

Foundry Lane Fitout

640m² of office and showroom rebuilt around a business that could not afford to close for a single trading day.

Service
Commercial Fitout
Size
640m²
Program
11 weeks
Days closed
0

The brief

Rebuild the tenancy without shutting it.

The client had signed a five-year extension on the condition the space was reconfigured: showroom to the front, open-plan work floor behind, four meeting rooms, a proper comms room and staff amenities that met the building's accessibility requirements.

Their constraint was absolute — the showroom takes appointments six days a week and the work floor runs a dispatch operation. Every quote they'd received assumed a three-week closure.

How we staged it

We split the tenancy into four zones and moved the business through them, one zone at a time, so there was always a trading showroom and a working dispatch area behind a sealed hoarding.

  • Noisy demolition, coring and overhead services work booked into after-hours windows agreed with the building manager six weeks ahead
  • Sealed acoustic hoardings with negative-pressure dust extraction between the live and construction zones
  • Temporary comms and power maintained through every zone change — the dispatch system never went down
  • Fire services isolated and re-certified zone by zone rather than in one shutdown
  • Deliveries scheduled outside customer hours through the loading dock, never the showroom
Eleven weeks, four zone moves, and the showroom took appointments every day it was scheduled to.

Base building and paperwork

The fitout application went in before we booked a single trade, along with our insurances, the subcontractor register and a site-specific safety plan matched to the building's induction requirements. Essential services certification, as-built drawings and the O&M manuals were issued as one indexed pack at practical completion — not chased for six weeks afterwards.

Finish

Exposed services with black-painted soffits, acoustic-rated glazed meeting rooms, a purpose-built comms room with dedicated cooling, and joinery shop-drawn and measured on site after the partitions were up.

Outcome

0 Trading days lost across eleven weeks
19 After-hours shifts absorbing the disruptive work
1 pack Certification, as-builts and manuals issued at completion